Route 100 Project: 4-23-20 Update

FALMOUTH - ROUTE 100 PROJECT

Construction Update #40 – April 23, 2020

The following information reflects the latest available information regarding the Route 100 Project in Falmouth. Please note that forward-looking information is based upon projections and is subject to change due to weather and other variables.

Note: Construction Updates will be provided on an as-needed basis, unless activities warrant more frequent updates.

 

WORK HOURS:

Work in the Route 100 Project zone will consist of normal construction working hours.

 

GENERAL OVERVIEW:

  • Multiple crews will be working on multiple facets of the project.
  • Special Note: The entire construction team is working under new guidelines related to Coronavirus. This is to ensure the safety of all employees and the general public.

 

WORK YOU’RE LIKELY TO SEE THE WEEKS OF APRIL 27TH AND MAY 4TH:

  • Shaw Brothers and their subcontractors will be:
    • Fine Tuning their work, cleaning up, and performing other miscellaneous activities.
    • Final Grading sidewalks and side slopes,
    • Placing seed on loamed areas.
    • Installing new street trees between Leighton Road and Mill Road.
  • Shaw Brothers, working for the Portland Water District, will be continuing new water main installation on Gray and Leighton Road.
    • Gray Road, between Leighton Road and Exit 53.
    • Leighton Road, west of Gray Road.
  • CPM Construction will resume working on the Libby Bridge, north of Mountain Road. Completion is anticipated over the next 2-3 weeks.

 

PHOTOS:

curb sidewalk

We've all been waiting to see what Route 100 will ultimately look like. With new curb, sidewalks prepared, and final grading done in most areas, it's starting to take shape. Gray Road, looking north from Bell Antiques.

curb sidewalk

Looking South, from Bell Antiques

curb sidewalk

Looking South, from Falmouth Road towards Mill Road.