Route 100 Project - 5-7-2020 Update

FALMOUTH - ROUTE 100 PROJECT

Construction Update #41 – May 7, 2020

The following information reflects the latest available information regarding the Route 100 Project in Falmouth. Please note that forward-looking information is based upon projections and is subject to change due to weather and other variables.

Note: Construction Updates will be provided on an as-needed basis, unless activities warrant more frequent updates.

 

WORK HOURS:

Work in the Route 100 Project zone will consist of normal construction working hours.

GENERAL OVERVIEW:

  • Multiple crews will be working on multiple facets of the project.
  • Special Note: The entire construction team is working under new guidelines related to Coronavirus. This is to ensure the safety of all employees and the general public.

WORK YOU’RE LIKELY TO SEE THE WEEKS OF MAY 11TH AND MAY 18TH:

  • Shaw Brothers and their subcontractors will be:
    • Installing Esplanade Biofilters on Gray Road. See photos below FMI.
    • Final Grading of sidewalks.
    • Continued fine-tuning of slopes, seeded areas, sidewalks, and esplanades.
    • W/O May 18th: Begin road prep for paving on Gray Road, between Leighton Road and Exit 53.
  • CPM Construction will continue and potentially complete their work on the Libby Bridge.
  • Shaw Brothers, working for the Portland Water District, will be:
    • Continuing and completing new water main and service line installations on Leighton Road.
    • W/O May 18th: Removal of temporary water lines on Gray and Leighton Roads.

PHOTOS:

esplanade biofilter prep

We haven’t talked about stormwater management yet. As part of the project, a series of esplanade biofilters are being installed along the roadway edges. Esplanade biofilters are strategically placed so that they collect stormwater runoff from the roadways and treat the stormwater before it enters the drainage system. Drainage from these systems eventually discharge to a waterbody, such as Hobbs Creek, the West Branch of the Piscataqua River, and the Presumpscot River. Photo’s above show the biofilters being assembled, prepared, and connected to the storm drain system.

biofilter detail

A plan view of the esplanade biofilters. Areas will be landscaped to further capture, filtrate, diffuse, and treat roadway runoff.