Construction Update #19 – August 1, 2019
The following information reflects the latest available information regarding the Route 100 Project in Falmouth. Please note that forward-looking information is based upon projections and is subject to change due to weather and other variables.
WORK HOURS:
Work in the Route 100 Project zone for the remainder of this week will begin at approximately 6:00 a.m. and last until approximately 5:00 p.m.; There is no after-hour/overnight work expected for next week.
GENERAL OVERVIEW:
- Completion of underground utility installations will be the general scope of work over the next few weeks.
- Traffic impacts are currently minimal, with one-lane alternating traffic occurring throughout most of the working/daytime hours.
- No road closures are anticipated over the next few weeks. However, an expected road closure that has been in planning stages is getting closer. A 1-week closure of Gray Road, north of Mountain Road, is tentatively planned for Monday, September 9th. Stay tuned for more info.
WORK CURRENTLY UNDERWAY:
As of Thursday, August 1st, crews were working on – or have completed – the following:
- Traffic:
- Mountain Road intersection: Traffic signals will be turned off during construction activities near the intersection. The intersections will be controlled by multiple flaggers during periods when construction is close to the intersection.
- Single-Lane Closures for various utility work will begin at 6:00 AM next week.
Motorists are encouraged to seek alternate routes during the peak/commuting hours.
- The speed limit remains reduced to 25 Miles-Per-Hour within the work zone areas.
- Summit Natural Gas’ sub-contractor is installing new natural gas infrastructure on Gray Road.
- Shaw Brothers are installing storm drain culverts on Gray Road near Bell Antiques.
- Shaw Brothers have been installing new storm drain infrastructure on Mountain Road.
WORK YOU’RE LIKELY TO SEE NEXT WEEK:
- Traffic: Same as previous week.
- Shaw Brothers will be installing new miscellaneous utility service lines on Gray Road in a multitude of locations.
- Shaw Brothers will begin installing new storm drain infrastructure on Falmouth Road.
- Summit Natural Gas will continue their work on their gas line expansion, heading northerly from Exit 53.
PHOTOS:
Shaw Brothers working on storm drain lines on Mountain Road.